Delgaz Grid launches an online application that will help improve the connection process

29 July 2022
Oil&Gas
energynomics

Delgaz Grid launched the “Work programs” application, as the first stage of the implementation of the SharePoint-type online platform “Electricity partners”, with the objective of improving the connection process and reducing its duration, the company announced.

By using the platform, which has been operational since July 1, the time to approve work schedules is reduced from five to two days for most types of work, while saving 1,750 man-hours per year. This means that important resources are freed up and can be further allocated to other process segments in order to reduce the duration of the connection process.

“The digitalization of distribution networks and processes are a priority for Delgaz Grid. The new platform responds both to the expectations of future users, to reduce the network access time, and to our contractors, to optimize the process of making the connection facilities,” said Cristian Secoșan, general manager of Delgaz Grid.

The application is dedicated to the approximately 250 contractors who perform electrical connections and allows the exchange of data and information between the parties involved. Thus, the process of submitting the request and approving the work programs is automated. Access to the platform is simple and secure, by creating an account, and the requested information is filled in predefined fields, with the possibility of attaching documents and comments.

Through this development, all six counties in which Delgaz Grid operates will have a unified way of working. On the platform, the traceability of the request will be ensured, from the date of submission, the stage and the date of approval of the work programs, and the necessary information will be automatically transmitted to all the people involved in the process of execution and reception of the works.

The platform was developed in about six months, by a Delgaz Grid project team, which included specialists in investment management, distribution network operation and IT solution development.

Delgaz Grid annually manages the creation of approximately 11,000 electrical connections for new consumers, and compliance with the 90-day deadline for the design, execution, reception and commissioning of the installations is a priority for the company.