German transmission system operator Tennet recently announced an 80% increase in its transmission fees because of the high construction costs of new power lines to accommodate renewable energy. A study of the Düsseldorf Institute for Competition Economics found that by 2025 costs of the Energiewende could exceed €25,000 for an average four-person household. Jeffrey Michel, independent energy expert, concludes that the Energiewende is running up against its limits – but may be saved by imported coal power from Central Europe, according to energypost.

Germany’s decision in 2011 to abandon nuclear power meant replacing 22% of the country’s electricity supplies by the end of 2022. With nine reactors since retired, that figure has dropped to 14%. Five of the remaining eight plants with a combined net capacity of 6.7 GW are located in southern Germany. New centralized gas power stations could replace some of that generation. The remainder must be superseded by local combined heat-and-power (CHP) plants, reduced demand, imported electricity, and renewable energy technologies.

The conditions for non-fossil power generation in Germany’s southern states are far from ideal, however. Solar power potential is limited with only 955 full-load hours of irradiation per year in Bavaria. The scarcity of historic windmills testifies to air currents too weak even to grind grain. Germany’s premier industrial region must therefore be re-energized by other means.

Storage could be a solution, but battery banks for storing solar energyare are only gradually being deployed, while hydroelectric pumped storage plants of up to 1,060 MW have become unprofitable due to depressed power trading prices. Cross-country transmission from large-scale photovoltaic and wind farms throughout Germany is therefore essential for filling the nuclear gap. However, the wide-ranging renewable power installations in north and eastern rural regions often generate excessive amounts of electricity simultaneously, necessitating expensive grid intervention measures.

Despite the impending need to supersede nuclear generation, transmission corridors from the North Sea to near Munich and Stuttgart are beset by planning delays. Overhead power lines are opposed by many for aesthetic and touristic reasons. Some people fear health detriments from electromagnetic radiation.

As a result, the German cabinet adopted a resolution in October 2015 to lay 1,000 km of long-distance cables underground. This was estimated at the time to cost €3 to €8 billion more than the overland option. TSO Tennet now expects total realization expenses of €4–5 billion for transmission from Saxony-Anhalt to Bavaria and €10 billion for the northern corridor to the southwest. These figures might be exceeded by the middle of the coming decade, however, if electricity usage in the transportation and building heating sectors rises beyond current estimates.

Underground power lines have other disadvantages. Although they carry direct current (DC) with radiation as harmless as the Earth’s magnetic field, and have no weight restrictions, repeated heating from power surges can lead to early failure. The rated service lifespan of 40 years is already only half that of overhead power lines.

The retirement of each southern German nuclear reactor will reduce net generating capacities by an average of 1.3 GW, necessitating precautionary measures against power blackouts. One option would be simply to raise electricity rates for lowering consumer demand. That alternative is favored by the European Commission to stimulate energy-efficient technologies and influence usage.

But costs to the consumer are already increasing of their own accord. Minimum investment returns of 9.05% for new transmission construction and 7.14% for refurbishment are currently guaranteed by the German federal network agency under the Grid Expansion Acceleration Act. Tennet, which operates the north-southeast transmission system, has announced an 80% increase of long-distance power transmission fees beginning next year, raising the annual price of electricity by about €30 for a three-person household. According to CEO Urban Keussen, the added cost is due to ongoing political controversies, tedious licensing, and public protests. In result, he has said, the “construction of power lines has not proceeded as rapidly as renewables deployment. That should alarm us.”

In a recent study of the Düsseldorf Institute for Competition Economics (DICE), overall expenses of €55.3 billion have been calculated for transmission and distribution by 2025. By that time, the average cumulative cost of the Energiewende could exceed €25,000 for an average four-person household, reports DICE.

The green power surcharge for households and small businesses has been raised by Germany’s network agency from 6.35 cents this year to 6.88 cents/kWh in 2017, mainly to compensate for falling wholesale power prices.

Wind power producers are also hurting from the lack of transmission capability. Last year, 4.1 TWh of wind energy could not be deliveredbecause of grid congestion. In consequence, the federal government now intends to restrict annual wind turbine construction from the 2.5 GW earlier anticipated to only 902 MW in the northern German states – Schleswig-Holstein and Mecklenburg-Vorpommern, Bremen and Hamburg, and adjacent regions of Lower Saxony. The regulation will be terminated automatically at the end of 2020.

Autor: Gabriel Avăcăriței

A journalist experienced with both old and new media, Gabriel has been the editor in chief of Energynomics since 2013. His great command in communication, organizing information and publishing are put to work every working day in order to develop all the projects of the Energynomics B2B communication platform: website, magazine, and own-events.