Gazprom is in discussions with banks as it looks to attract in 2020 project financing of US$14 billion for the construction of its Amur gas processing plant, which will be Russia’s largest and the second-largest in the world, Gazprom manager Alexander Ivannikov, who is responsible for the company’s financial and economic policy, told Russian media on Monday.
Gazprom has reached agreements with export agencies, which are ready to provide guarantees for US$7 billion, and talks with banks are ongoing, Ivannikov said, according to oilprice.com.
This year, Gazprom won’t need funds for the Amur gas processing plant because its financing needs have been covered by bridge loans, the manager noted.
The plant is designed to be a crucial link along the Power of Siberia gas pipeline with which Gazprom plans to begin delivering gas to China in December 2019.
Construction at the Amur gas processing plant started back in 2015. As of the end of December 2018, the progress on the gas processing plant’s construction was at 24 percent, according to Alexey Miller, the chairman of Gazprom’s Management Committee.
The Amur gas processing plant will have a design capacity of 42 billion cubic meters of gas per year. The plant is planned to have six production lines, and the first two lines are currently scheduled for commissioning in 2021. The Amur gas processing plant will also host the largest helium production facility in the world, according to the Russian gas giant.