WALDEVAR Energy announces that the contracted volume of 481 MW is scheduled to be completed by April 2024. In 2023, the company completed more than 30 PV projects totaling 184 MW.
These include the 63 MWp Călugăreni project owned by PPC Renewables Romania with Metka EGN Mytilineos as EPC and the Roata project owned by Alerion with Sunnerg Renewable Service as EPC. More projects are described on the website www.waldevar.com.
With a construction capacity of 2.5 MW per day, WALDEVAR Energy “is proof of commitment and excellence in promoting a greener future and continuously reducing the cost of energy”, says Christian Leonte, Business Development Director WALDEVAR Energy S.R.L.
The company has over 600 specialists and its own fleet of over 65 ramming machines dedicated to the construction of photovoltaic parks. WALDEVAR Energy offers complete design services, specialised studies, specific civil construction, installation of fixed structures and tracker systems, equipment, testing and commissioning of photovoltaic systems. The company also provides efficient connection to the electricity grid, including work on the high-voltage grid, with ANRE authorisation. WALDEVAR Energy’s offer is complemented by post-installation maintenance services, guaranteeing optimal operation of the photovoltaic plants.